Development Chart - Product Name ​

Template IDLocal ID
Template VersionVersion
ApprovalApprover name

Responsibilities are defined in development-plan. Bold responsibility IDs identify the lead.

Definitions ​

TermDefinition
PHAPreliminary hazard analysis
FMEAFailure mode and effects analysis

1. Product planning ​

1.1 Idea collection ​

No.Work PackageResponsibilityDepends On
1.1Idea collectionTM_1—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M1 General product characteristicsDay-Month-YearDay-Month-Year—

1.2 Product specification ​

No.Work PackageResponsibilityDepends On
1.2Product specificationTM_11.1
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M2 Product specification documented in intended-use
M3 Product classification documented in mdr-classification
Day-Month-YearDay-Month-Year—

1.3 Market analysis ​

No.Work PackageResponsibilityDepends On
1.3Market analysisTM_4, TM_51.2
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M4 Market analysis documented in market-analysisDay-Month-YearDay-Month-Year—

1.4 Risk management planning ​

No.Work PackageResponsibilityDepends On
1.4Risk management planningTM_4, TM_5—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M5 Risk management plan documented in risk-management-plan
M6 schedule for risk management activities
M7 risk acceptance matrix documented in risk-table
M8 initial preliminary hazard analysis documented in risk-table according to risk-management-plan
M9 initial process risk analysis documented in risk-table
Day-Month-YearDay-Month-Year—

1.5 Development planning ​

No.Work PackageResponsibilityDepends On
1.5Development planningTM_5—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M10 Development plan documented in development-plan
M11 Test plan documented in test-plan
Day-Month-YearDay-Month-Year—

1.6 Notification of in-house software ​

No.Work PackageResponsibilityDepends On
1.6Notification of in-house softwareTM_1—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M12 local notification form for in-house softwareDay-Month-YearDay-Month-Year—

2. Stakeholder requirements ​

2.1 Stakeholder requirements ​

No.Work PackageResponsibilityDepends On
2.1Stakeholder requirementsTM_4, TM_11.1 and 1.2
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M13 Stakeholder requirements documented in stakeholder-requirementsDay-Month-YearDay-Month-Year—

2.2 Failure mode and effects analysis (FMEA) ​

No.Work PackageResponsibilityDepends On
2.2Failure mode and effects analysis (FMEA)TM_2, TM_3, TM_51.4 and 2.1
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M14 FMEA documented in risk-table based on PHADay-Month-YearDay-Month-Year—

2.3 Update test plan ​

No.Work PackageResponsibilityDepends On
2.3Update test planTM_2, TM_3, TM_51.5 and 2.1
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M15 Updated test-plan
M16 Acceptance-test specifications documented in test-specifications
Day-Month-YearDay-Month-Year—

2.4 Review stakeholder requirements ​

No.Work PackageResponsibilityDepends On
2.4Review stakeholder requirementsTM_52
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M17 Stakeholder requirements review documented in stakeholder-requirements-reviewDay-Month-YearDay-Month-Year—

3. System requirements ​

3.1 System requirements ​

No.Work PackageResponsibilityDepends On
3.1System requirementsTM_41.2, 2.1/2.4, 2.2
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M18 System requirements documented in system-requirementsDay-Month-YearDay-Month-Year—

3.2 Update FMEA ​

No.Work PackageResponsibilityDepends On
3.2Update FMEATM_2, TM_3, TM_52.2 and 3.1
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M19 Updated FMEA documented in risk-tableDay-Month-YearDay-Month-Year—

3.3 Update test plan ​

No.Work PackageResponsibilityDepends On
3.3Update test planTM_2, TM_3, TM_52.3 and 3.1
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M20 Updated test-plan
M21 System-test specifications documented in test-specifications
Day-Month-YearDay-Month-Year—

3.4 Review system requirements ​

No.Work PackageResponsibilityDepends On
3.4Review system requirementsTM_53
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M22 System requirements review documented in system-requirements-reviewDay-Month-YearDay-Month-Year—

4. Architecture and design ​

4.1 Architecture and design ​

No.Work PackageResponsibilityDepends On
4.1Architecture and designTM_2, TM_43.1/3.4
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M23 Architecture and design documented in architectureDay-Month-YearDay-Month-Year—

4.2 SOUP ​

No.Work PackageResponsibilityDepends On
4.2SOUPTM_2, TM_3, TM_4—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M24 SOUP list documented in soup-listDay-Month-YearDay-Month-Year—

4.3 Update FMEA ​

No.Work PackageResponsibilityDepends On
4.3Update FMEATM_2, TM_3, TM_53.2 and 4.1
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M25 Updated FMEA documented in risk-tableDay-Month-YearDay-Month-Year—

4.4 Update test plan ​

No.Work PackageResponsibilityDepends On
4.4Update test planTM_2, TM_3, TM_53.3 and 4.1
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M26 Updated test-plan
M27 Integration- and unit-test specifications documented in test-specifications
Day-Month-YearDay-Month-Year—

4.5 Review architecture and design ​

No.Work PackageResponsibilityDepends On
4.5Review architecture and designTM_54
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M28 Architecture and design review documented in architecture-reviewDay-Month-YearDay-Month-Year—

5. Implementation ​

5.1 Implementation of architecture and design ​

No.Work PackageResponsibilityDepends On
5.1Implementation of architecture and designTM_2, TM_34.1/4.5
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduled—
2026————
MilestonesDeadlineDate AchievedComment
M29 Software units according to development-planDay-Month-YearDay-Month-Year—

6. Unit and integration tests ​

6.1 Verification of unit tests ​

No.Work PackageResponsibilityDepends On
6.1Verification of unit testsTM_2, TM_3, TM_54.4 and 5.1
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026Scheduled———
MilestonesDeadlineDate AchievedComment
M30 Unit-test protocol documented in test-protocol-UIT
M31 Test report documented in test-report
Day-Month-YearDay-Month-Year—

6.2 Integration of verified software units ​

No.Work PackageResponsibilityDepends On
6.2Integration of verified software unitsTM_2, TM_3, TM_56.1
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026Scheduled———
MilestonesDeadlineDate AchievedComment
M32 Work step "All verified software units are integrated into the code base according to development-plan" completedDay-Month-YearDay-Month-Year—

6.3 Verification of system integration ​

No.Work PackageResponsibilityDepends On
6.3Verification of system integrationTM_2, TM_3, TM_54.4 and 6.2
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026Scheduled———
MilestonesDeadlineDate AchievedComment
M33 Integration-test protocol documented in test-protocol-UIT
M34 Updated test-report
M35 Integrated system
Day-Month-YearDay-Month-Year—

7. System tests ​

7.1 Verification of integrated system ​

No.Work PackageResponsibilityDepends On
7.1Verification of integrated systemTM_2, TM_4, TM_53.3 and 6.3
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026Scheduled———
MilestonesDeadlineDate AchievedComment
M36 System-test protocol documented in test-protocol-ST
M37 Updated test-report
M38 Verified integrated system
Day-Month-YearDay-Month-Year—

8. Acceptance tests ​

8.1 Validation of verified integrated system ​

No.Work PackageResponsibilityDepends On
8.1Validation of verified integrated systemTM_1, TM_3, TM_42.3 and 7.1
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026————
MilestonesDeadlineDate AchievedComment
M39 Acceptance-test protocol documented in test-protocol-AT
M40 Finalized test-report
M41 Release candidate
Day-Month-YearDay-Month-Year—

9. Product release ​

9.1 Risk evaluation ​

No.Work PackageResponsibilityDepends On
9.1Risk evaluationTM_4, TM_51.4 and 8.1
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026————
MilestonesDeadlineDate AchievedComment
M42 Risk management report documented in risk-management-reportDay-Month-YearDay-Month-Year—

9.2 Instructions for use ​

No.Work PackageResponsibilityDepends On
9.2Instructions for useTM_4—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026————
MilestonesDeadlineDate AchievedComment
M43 Preparation and provision of instructions-for-useDay-Month-YearDay-Month-Year—

9.3 Release checklist ​

No.Work PackageResponsibilityDepends On
9.3Release checklistTM_1, TM_6—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026————
MilestonesDeadlineDate AchievedComment
M44 Release checklist documented in checklist-releaseDay-Month-YearDay-Month-Year—

9.4 Internal information ​

No.Work PackageResponsibilityDepends On
9.4Internal informationTM_1, TM_6—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026————
MilestonesDeadlineDate AchievedComment
M45 Information regarding release of the in-house software to the local IT department, local medical technology department, local quality management department, and local legal departmentDay-Month-YearDay-Month-Year—

9.5 Public declaration ​

No.Work PackageResponsibilityDepends On
9.5Public declarationTM_1, TM_6—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026Scheduled———
MilestonesDeadlineDate AchievedComment
M46 Public declaration according to the local public-declaration templateDay-Month-Year——

9.6 Update local medical device list ​

No.Work PackageResponsibilityDepends On
9.6Update local medical device listTM_1—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026Scheduled———
MilestonesDeadlineDate AchievedComment
M47 Updated local medical device list (= local medical device inventory)Day-Month-YearDay-Month-Year—

9.7 Release notes ​

No.Work PackageResponsibilityDepends On
9.7Release notesTM_2, TM_5—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026Scheduled———
MilestonesDeadlineDate AchievedComment
M48 Release notes according to the local release-notes templateDay-Month-Year——

9.8 Deployment ​

No.Work PackageResponsibilityDepends On
9.8DeploymentTM_4, TM_5—
YearQ1Q2Q3Q4
2025ScheduledScheduledScheduledScheduled
2026Scheduled———
MilestonesDeadlineDate AchievedComment
M49 Deployment procedure as documented in deployment
M50 In-house medical device software in operation
Day-Month-YearDay-Month-Year—