Development Chart - Product Name
| Template ID | Local ID |
| Template Version | Version |
| Approval | Approver name |
Responsibilities are defined in development-plan. Bold responsibility IDs identify the lead.
Definitions
| Term | Definition |
|---|---|
| PHA | Preliminary hazard analysis |
| FMEA | Failure mode and effects analysis |
1. Product planning
1.1 Idea collection
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 1.1 | Idea collection | TM_1 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M1 General product characteristics | Day-Month-Year | Day-Month-Year | — |
1.2 Product specification
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 1.2 | Product specification | TM_1 | 1.1 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M2 Product specification documented in intended-use M3 Product classification documented in mdr-classification | Day-Month-Year | Day-Month-Year | — |
1.3 Market analysis
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 1.3 | Market analysis | TM_4, TM_5 | 1.2 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M4 Market analysis documented in market-analysis | Day-Month-Year | Day-Month-Year | — |
1.4 Risk management planning
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 1.4 | Risk management planning | TM_4, TM_5 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M5 Risk management plan documented in risk-management-plan M6 schedule for risk management activities M7 risk acceptance matrix documented in risk-table M8 initial preliminary hazard analysis documented in risk-table according to risk-management-plan M9 initial process risk analysis documented in risk-table | Day-Month-Year | Day-Month-Year | — |
1.5 Development planning
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 1.5 | Development planning | TM_5 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M10 Development plan documented in development-plan M11 Test plan documented in test-plan | Day-Month-Year | Day-Month-Year | — |
1.6 Notification of in-house software
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 1.6 | Notification of in-house software | TM_1 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M12 local notification form for in-house software | Day-Month-Year | Day-Month-Year | — |
2. Stakeholder requirements
2.1 Stakeholder requirements
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 2.1 | Stakeholder requirements | TM_4, TM_1 | 1.1 and 1.2 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M13 Stakeholder requirements documented in stakeholder-requirements | Day-Month-Year | Day-Month-Year | — |
2.2 Failure mode and effects analysis (FMEA)
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 2.2 | Failure mode and effects analysis (FMEA) | TM_2, TM_3, TM_5 | 1.4 and 2.1 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M14 FMEA documented in risk-table based on PHA | Day-Month-Year | Day-Month-Year | — |
2.3 Update test plan
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 2.3 | Update test plan | TM_2, TM_3, TM_5 | 1.5 and 2.1 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M15 Updated test-plan M16 Acceptance-test specifications documented in test-specifications | Day-Month-Year | Day-Month-Year | — |
2.4 Review stakeholder requirements
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 2.4 | Review stakeholder requirements | TM_5 | 2 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M17 Stakeholder requirements review documented in stakeholder-requirements-review | Day-Month-Year | Day-Month-Year | — |
3. System requirements
3.1 System requirements
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 3.1 | System requirements | TM_4 | 1.2, 2.1/2.4, 2.2 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M18 System requirements documented in system-requirements | Day-Month-Year | Day-Month-Year | — |
3.2 Update FMEA
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 3.2 | Update FMEA | TM_2, TM_3, TM_5 | 2.2 and 3.1 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M19 Updated FMEA documented in risk-table | Day-Month-Year | Day-Month-Year | — |
3.3 Update test plan
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 3.3 | Update test plan | TM_2, TM_3, TM_5 | 2.3 and 3.1 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M20 Updated test-plan M21 System-test specifications documented in test-specifications | Day-Month-Year | Day-Month-Year | — |
3.4 Review system requirements
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 3.4 | Review system requirements | TM_5 | 3 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M22 System requirements review documented in system-requirements-review | Day-Month-Year | Day-Month-Year | — |
4. Architecture and design
4.1 Architecture and design
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 4.1 | Architecture and design | TM_2, TM_4 | 3.1/3.4 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M23 Architecture and design documented in architecture | Day-Month-Year | Day-Month-Year | — |
4.2 SOUP
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 4.2 | SOUP | TM_2, TM_3, TM_4 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M24 SOUP list documented in soup-list | Day-Month-Year | Day-Month-Year | — |
4.3 Update FMEA
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 4.3 | Update FMEA | TM_2, TM_3, TM_5 | 3.2 and 4.1 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M25 Updated FMEA documented in risk-table | Day-Month-Year | Day-Month-Year | — |
4.4 Update test plan
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 4.4 | Update test plan | TM_2, TM_3, TM_5 | 3.3 and 4.1 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M26 Updated test-plan M27 Integration- and unit-test specifications documented in test-specifications | Day-Month-Year | Day-Month-Year | — |
4.5 Review architecture and design
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 4.5 | Review architecture and design | TM_5 | 4 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M28 Architecture and design review documented in architecture-review | Day-Month-Year | Day-Month-Year | — |
5. Implementation
5.1 Implementation of architecture and design
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 5.1 | Implementation of architecture and design | TM_2, TM_3 | 4.1/4.5 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | — |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M29 Software units according to development-plan | Day-Month-Year | Day-Month-Year | — |
6. Unit and integration tests
6.1 Verification of unit tests
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 6.1 | Verification of unit tests | TM_2, TM_3, TM_5 | 4.4 and 5.1 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | Scheduled | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M30 Unit-test protocol documented in test-protocol-UIT M31 Test report documented in test-report | Day-Month-Year | Day-Month-Year | — |
6.2 Integration of verified software units
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 6.2 | Integration of verified software units | TM_2, TM_3, TM_5 | 6.1 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | Scheduled | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M32 Work step "All verified software units are integrated into the code base according to development-plan" completed | Day-Month-Year | Day-Month-Year | — |
6.3 Verification of system integration
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 6.3 | Verification of system integration | TM_2, TM_3, TM_5 | 4.4 and 6.2 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | Scheduled | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M33 Integration-test protocol documented in test-protocol-UIT M34 Updated test-report M35 Integrated system | Day-Month-Year | Day-Month-Year | — |
7. System tests
7.1 Verification of integrated system
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 7.1 | Verification of integrated system | TM_2, TM_4, TM_5 | 3.3 and 6.3 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | Scheduled | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M36 System-test protocol documented in test-protocol-ST M37 Updated test-report M38 Verified integrated system | Day-Month-Year | Day-Month-Year | — |
8. Acceptance tests
8.1 Validation of verified integrated system
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 8.1 | Validation of verified integrated system | TM_1, TM_3, TM_4 | 2.3 and 7.1 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M39 Acceptance-test protocol documented in test-protocol-AT M40 Finalized test-report M41 Release candidate | Day-Month-Year | Day-Month-Year | — |
9. Product release
9.1 Risk evaluation
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 9.1 | Risk evaluation | TM_4, TM_5 | 1.4 and 8.1 |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M42 Risk management report documented in risk-management-report | Day-Month-Year | Day-Month-Year | — |
9.2 Instructions for use
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 9.2 | Instructions for use | TM_4 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M43 Preparation and provision of instructions-for-use | Day-Month-Year | Day-Month-Year | — |
9.3 Release checklist
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 9.3 | Release checklist | TM_1, TM_6 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M44 Release checklist documented in checklist-release | Day-Month-Year | Day-Month-Year | — |
9.4 Internal information
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 9.4 | Internal information | TM_1, TM_6 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | — | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M45 Information regarding release of the in-house software to the local IT department, local medical technology department, local quality management department, and local legal department | Day-Month-Year | Day-Month-Year | — |
9.5 Public declaration
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 9.5 | Public declaration | TM_1, TM_6 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | Scheduled | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M46 Public declaration according to the local public-declaration template | Day-Month-Year | — | — |
9.6 Update local medical device list
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 9.6 | Update local medical device list | TM_1 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | Scheduled | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M47 Updated local medical device list (= local medical device inventory) | Day-Month-Year | Day-Month-Year | — |
9.7 Release notes
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 9.7 | Release notes | TM_2, TM_5 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | Scheduled | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M48 Release notes according to the local release-notes template | Day-Month-Year | — | — |
9.8 Deployment
| No. | Work Package | Responsibility | Depends On |
|---|---|---|---|
| 9.8 | Deployment | TM_4, TM_5 | — |
| Year | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|
| 2025 | Scheduled | Scheduled | Scheduled | Scheduled |
| 2026 | Scheduled | — | — | — |
| Milestones | Deadline | Date Achieved | Comment |
|---|---|---|---|
| M49 Deployment procedure as documented in deployment M50 In-house medical device software in operation | Day-Month-Year | Day-Month-Year | — |